KPI
Transcript: Qty (No mandatory and No recommended) Total equipment : 66,474 Mandatory equipment: 15 Recommended equipment: 208 KPI selected equipment : ~18,400 Slected equipment percentage: 27% CNCEC discount suggestion: 49,989,649 US$ Mandatory and Recomended: ~19,000,000 US$ slected equipment after technical evaluation: ~9,149,403 US$ Percentage : ~19 % (based on total CNCEC offer) * This is not final result and we will still working on it because of CNCEC incomplete answer Progress How many equipment are checked ? Vendor evaluation (Based on CNCEC proposal) Dated 26/03/2016 1)Delayed answer from CNCEC . 2)No QC/QA specialist inKPI. 3)Some general information without any particular location in proposed discount from CNCEC Procurement Evaluation (example) Technical Evaluation (example) Reason of delay Potential Amount: Preliminary calculation 35,761,095 US$ New calcualtion after technical evaluation: ~30,000,000 US$ Summery of calculation: Progress till 26/03/2016